- Designed the 8-inch PVC influent, 129 gpm lift station, back-up generator, and 4-inch force main.
- Managed construction
- Leading the efforts to decommission an antiquated treatment plant near the lift station while working closely with GA EPD to ensure optimal protection of our environment.
- Reductions in energy costs resulted from due diligence in the design phase of the 5500 to 6000 lf of 4-inch diameter C-900 PVC forcemain; a portion of the flow was able to gravity flow after PCG prudently reviewed the best options for the alignment.